Plan Review Notes
Plan Review Notes For Permit 20120145
Permit Number 20120145
Review Stop BUILDING
Sequence Number 2
Notes
Date Text
2021-04-05 15:20:25.00000REPLACE SHEET 07:
 1] CHANGE CONDUCTOR BETWEEN 7600W INVERTER AND COMBINER
 PANEL TO #8 CU. AMPACITY IS DETERMINED BASED ON 75
 DEGREES C TERMINAL TEMPERATURE, ASSUMED ON INVERTER AND
 CIRCUIT BREAKER. #10 IS RATED FOR 40A ONLY AT 90
 DEGREES C.
 2] 3/0 CONDUCTORS BETWEEN SERVICE PANEL AND GATEWAY,
 AND BETWEEN GATEWAY AND 200A SUBPANEL, ARE IDENTIFIED
 AS "PV WIRE" ON SCHEDULE. SHOW AS THWN-2.
 3] SHOW CONDUIT/CONDUCTORS FROM TESLA GENERATION PANEL
 TO POWERWALLS.
 4] ADD NOTE INDICATING THAT GUTTER SPACE IN SERVICE
 PANEL WILL NOT BE FILLED MORE THAN 75% DUE TO TAPS TO
 EXISTING FEEDERS
  
 PROVIDE SPECIFICATION SHEETS FOR TESLA GATEWAY &
 POWERWALLS
  
  
2021-04-05 12:54:35.00000REVISIONS DROPPED OFF