Plan Review Details - Permit 25101013
Plan Review Stops For Permit 25101013
Review Stop BUILDING BUILDING DEPARTMENT
Rev No 2 Status A Date 11-20-2025 Cont ID  
Sent By cdorman Date 11-20-2025 Time 16:22 Rev Time 0.00
Received By cdorman Date 11-13-2025 Time 09:53 Sent To  
Notes
2025-11-13 09:53:46.00000REVISION PERMITS@SUNVENA.COM

Review Stop BUILDING BUILDING DEPARTMENT
Rev No 1 Status D Date 10-30-2025 Cont ID  
Sent By cdorman Date 10-30-2025 Time 15:54 Rev Time 0.00
Received By cdorman Date 10-30-2025 Time 08:15 Sent To  
Notes
2025-11-05 09:25:53.00000FULL PAYMENT RECEIVED REFERENCE NUMBER:16888174
2025-11-03 08:12:16.00000NOC: OR BK 3153 PG 1595
2025-10-30 15:54:41.00000SHEET E03:
 1] REMOVE LABEL SHOWN AT TOP OF SHEET (MAX VOLTAGE/MAX
 CIRC CURRENT, ETC.). NOT APPLICABLE TO THIS
 INSTALLATION.
 2] CHANGE AC CURRENT LABEL TO SHOW ACTUAL MAXIMUM
 COMBINED INVERTER OUTPUT OF 20.54 A.
  
2025-10-30 08:16:52.00000PERMITS@SUNVENA.COM