Plan Review Details - Permit 25070243
Plan Review Stops For Permit 25070243
Review Stop BUILDING BUILDING DEPARTMENT
Rev No 2 Status A Date 08-05-2025 Cont ID  
Sent By cshackel Date 08-05-2025 Time 15:43 Rev Time 0.00
Received By ERIC Date 07-09-2025 Time 15:44 Sent To  
Notes
***NONE***

Review Stop BUILDING BUILDING DEPARTMENT
Rev No 1 Status C Date 07-09-2025 Cont ID  
Sent By cdorman Date 07-09-2025 Time 14:59 Rev Time 0.00
Received By cdorman Date 07-09-2025 Time 08:36 Sent To  
Notes
2025-07-09 14:59:00.00000ELECTRICAL SHEETS APPROVED. FULL APPROVAL CONDITIONAL
 ON STRUCTURAL REVIEW.
2025-07-09 08:36:39.00000HUTCHINSONCONTRACTORS@YAHOO.COM

Review Stop ENGINEER SITE & DRAINAGE FDO
Rev No 1 Status C Date 07-09-2025 Cont ID  
Sent By hlopez Date 07-09-2025 Time 08:37 Rev Time 0.00
Received By hlopez Date 07-09-2025 Time 08:37 Sent To  
Notes
2025-07-09 08:37:58.00000FEBRUARY 3, 2025
 JEREMY D. SHARIT, P.E.
 SMW ENGINEERING, INC.
 458 BUSINESS CENTER DRIVE
 BIRMINGHAM, AL 35244
 SUBJECT: COMMERCIAL SITE PLAN EXEMPTION VERIFICATION –
 CONDITIONALLY-APPROVED
 PROJECT NAME: DESOTOCITY FL
 LATITUDE: 27° 24’55.36`” N (NAD 83)
 LONGITUDE: 81° 24’ 55.36” W (NAD 83)
 PARCEL ID NO.: C-22-35-29-020-0751-0000
 REFERENCE NO.: 24120029
 REFERENCES: SECTION 12.04.207 COMMERCIAL SITE PLAN
 EXEMPTION VERIFICATION AND 12.04.215 ANTENNAS AND
 GROUND MOUNTED TOWERS HIGHLANDS COUNTY LAND DEVELOPMENT
 REGULATIONS (LDR’S), CURRENT EDITION.
 DEAR MR. SHARIT,
 WE HAVE REVIEWED YOUR REQUEST FOR AN EXEMPTION TO THE
 REQUIREMENT TO PROVIDE PRELIMINARY AND FINAL SITE
 PLANS, AS REQUIRED BY THE LDR’S, FOR THE ABOVE SUBJECT
 PROJECT. YOUR REQUEST IS CONDITIONALLY-APPROVED AS
 MEETING THE REQUIRED FINDINGS FOR AN EXEMPTION. OUR
 OFFICE HAS ALSO REVIEWED THE PROPOSED SITE PLAN AND
 SUPPORTING DOCUMENTS AND FINDS THAT THE SITE IS IN
 COMPLIANCE WITH SECTION 12.04.215 ANTENNAS AND GROUND
 MOUNTED TOWERS OF THE LDR’S.
 PLEASE BE ADVISED THAT THE FOLLOWING INFORMATION MUST
 BE SUBMITTED TO OUR OFFICE PRIOR TO THE BUILDING
 DEPARTMENT ISSUING THE CERTIFICATE OF COMPLETION:
 • A CERTIFICATE OF COMPLIANCE SHALL BE SUBMITTED TO OUR
 OFFICE ONCE THE IMPROVEMENTS HAVE BEEN COMPLETED;
 YOU MAY KNOW PROCEED WITH OBTAINING A BUILDING PERMIT.
 IF YOU SHOULD HAVE ANY QUESTIONS OR CONCERNS, PLEASE
 CONTACT OUR OFFICE AT (863) 402-6877.
 SINCERELY,
 DEMITRIA “DENA” PETERSON

Copyright © 2008 – THE PLUS SERIES ® – All Rights Reserved