Plan Review Details - Permit 25030106
Plan Review Stops For Permit 25030106
Review Stop FIRE FIRE DEPARTMENT
Rev No 1 Status A Date 03-11-2025 Cont ID  
Sent By cshackel Date 03-11-2025 Time 15:26 Rev Time 0.00
Received By cshackel Date 03-05-2025 Time 10:55 Sent To  
Notes
2025-03-11 15:29:27.00000PLAN REVIEW #: 25030106
 PROJECT: AMAZON - UNDERGROUND
 LOCATION: 1249 US 27
 OCCUPANCY: STORAGE
 REVIEWED BY: JASON RAPER, DIVISION CHIEF FIRE MARSHAL
 DATE: MARCH 11, 2025
 PLANS WERE REVIEWED UTILIZING THE FLORIDA FIRE
 PREVENTION CODE (FFPC), FLORIDA STATUTE, FLORIDA
 ADMINISTRATIVE RULE, AND ANY REFERENCE NFPA CODE OR
 STANDARD. _____________________________________________
 _______________________________ APPROVED – WITH NOTES –
 INSPECTIONS REQUIRED THRUST BLOCKING, RESTRAINTS,
 PRESSURE TEST, AND FLOW TEST
 FOLLOW ALL REQUIREMENTS WITH HIGHLANDS COUNTY –
 TECHNICAL STANDARDS MANUAL – SECTION FOUR PUBLIC WATER
 SYSTEM DESIGN AND CONSTRUCTION STANDARDS
 HTTPS://LIBRARY.MUNICODE.COM/FL/HIGHLANDS_COUNTY/CODES/
 TECHNICAL_STANDARDS_MANUAL
 ANCHORS: CONCRETE THRUST BLOCKS SHALL BE PLACED AT ALL
 BENDS, TEES, PLUGS, AND OTHER FITTINGS TO PROVIDE
 LATERAL SUPPORT. THRUST BLOCKS SHALL CONFORM TO THE
 DETAILS SHOWN ON THE ILLUSTRATIVE STANDARDS. CONCRETE
 SHALL HAVE A COMPRESSIVE STRENGTH OF 2500 PSI AFTER 28
 DAYS, AND SHALL HAVE A MINIMUM CURING TIME OF 3 DAYS.
 THE POURED CONCRETE SHALL BE LEFT EXPOSED FOR A MINIMUM
 OF 24 HOURS BEFORE BACKFILLING AND NOT MORE THAN 48
 HOURS.
 FLUSHING: ALL WATER MAINS SHALL BE FLUSHED TO REMOVE
 ALL SAND AND OTHER FOREIGN MATTER. THE VELOCITY OF THE
 FLUSHING WATER SHALL BE AT LEAST 2.5 FEET PER SECOND.
 FLUSHING SHALL BE TERMINATED AT THE DIRECTION OF THE
 PROJECT ENGINEER. THE CONTRACTOR SHALL DISPOSE OF THE
 FLUSHING WATER WITHOUT CAUSING A NUISANCE OR PROPERTY
 DAMAGE.
 1. S.
 HYDROSTATIC TESTS:
 1. ALL COMPONENTS OF THE WATER DISTRIBUTION SYSTEM,
 INCLUDING FITTINGS, HYDRANTS, SERVICES, CONNECTIONS,
 AND VALVES SHALL BE HYDROSTATIC TESTED. SPECIFIC
 DISTRIBUTION SYSTEM COMPONENTS INCLUDING FITTINGS,
 VALVES, AND HYDRANTS, SHALL REMAIN UNCOVERED UNTIL
 TESTED AND APPROVED, PROVIDED, HOWEVER, THAT PIPE
 TRENCHES UNDER TRAVELED STREETS OR ROADS MAY BE
 BACKFILLED WITH THE PERMISSION OF THE PROJECT ENGINEER.
 NO TESTING SHALL BE DONE UNTIL ALL CONCRETE TRUST
 BLOCKING IS IN PLACE AND SET. IF HIGH EARLY STRENGTH
 CONCRETE IS USED, TESTING MAY BE CONDUCTED 48 HOURS
 AFTER THE CONCRETE IS PLACED; OTHERWISE, TRUST BLOCK
 CONCRETE MUST CURE 5 DAYS BEFORE PRESSURE TESTING
 COMMENCES. IN TESTING, THE PART OF THE SYSTEM UNDER
 TEST SHALL BE FILLED WITH POTABLE WATER AND SUBJECTED
 TO A SUSTAINED PRESSURE OF 150 PSI. THE PIPING SHALL BE
 TESTED IN SECTIONS, THEREBY