-     My Account  
   

Log in is not required to search. In the red banner above select: I Want To > Search > Permits

Plan Review Details - Permit 24070245
Plan Review Stops For Permit 24070245
Review Stop BUILDING BUILDING DEPARTMENT
Rev No 3 Status A Date 10-01-2024 Cont ID  
Sent By cdorman Date 10-01-2024 Time 14:25 Rev Time 0.00
Received By cdorman Date 09-27-2024 Time 10:36 Sent To  
Notes
2024-09-27 09:22:12.00000PERMITSARASOTA@FREEDOMFOREVER.COM

Review Stop BUILDING BUILDING DEPARTMENT
Rev No 2 Status A Date 07-31-2024 Cont ID  
Sent By cdorman Date 07-31-2024 Time 14:58 Rev Time 0.00
Received By cdorman Date 07-22-2024 Time 10:37 Sent To  
Notes
2024-08-06 10:21:50.00000SENT PAYMENT REQ
2024-07-22 10:38:11.00000CORRECTED PLANS PERMITSARASOTA@FREEDOMFOREVER.COM

Review Stop BUILDING BUILDING DEPARTMENT
Rev No 1 Status R Date 07-09-2024 Cont ID  
Sent By cdorman Date 07-09-2024 Time 15:10 Rev Time 0.00
Received By cdorman Date 07-09-2024 Time 14:42 Sent To  
Notes
2024-07-09 15:10:36.00000SHEET PV 4 INDICATES THE USE OF TWO POLES OF A QUAD
 BREAKER TO INTERCONNECT AN EXISTING PV SYSTEM, ALONG
 WITH A NEW BACKFED BREAKER TO INTERCONNECT THE PROPOSED
 SYSTEM.
 THE RELATIVE LOCATION OF THESE TWO CIRCUIT BREAKERS IS
 UNCLEAR; PLEASE PROVIDE ONE OF THE FOLLOWING TWO
 SOLUTIONS:
 1] INCLUDE PLAN LANGUAGE INDICATING THAT BOTH CIRCUIT
 BREAKERS WILL BE LOCATED ON THE OPPOSITE END OF THE BUS
 FROM THE MAIN (HORIZONTALLY SIDE-BY-SIDE), OR
 2] REDESIGN DRAWING TO COMBINE BOTH THE EXISTING AND
 PROPOSED PV SYSTEMS PRIOR TO ENTERING THE SERVICE
 PANEL. THIS METHOD WILL SHOW A SINGLE POINT OF
 INTERCONNECTION.