Plan Review Details - Permit 24030618
Plan Review Stops For Permit 24030618
Review Stop BUILDING BUILDING DEPARTMENT
Rev No 3 Status A Date 05-02-2024 Cont ID  
Sent By cdorman Date 05-02-2024 Time 15:41 Rev Time 0.00
Received By cdorman Date 04-17-2024 Time 15:39 Sent To  
Notes
2024-04-17 15:39:58.00000REVISED PLAN KELCIE@CASTAWAYSENERGY.COM

Review Stop BUILDING BUILDING DEPARTMENT
Rev No 2 Status D Date 04-10-2024 Cont ID  
Sent By elthomps Date 04-10-2024 Time 15:51 Rev Time 0.00
Received By elthomps Date 04-05-2024 Time 14:57 Sent To  
Notes
2024-04-09 08:49:42.00000TO USE BACKFED BREAKER IN COMBINER PANEL AS PV
 DISCONNECT/RAPID SHUTDOWN INITIATION, THE FOLLOWING
 ITEMS MUST BE INDICATED ON THE PLANS (SHEET E-601):
  
 1] INSTALL LISTED HOLD-DOWN DEVICE FOR BACKFED BREAKER,
 IN COMPLIANCE WITH 408.36 (D). FOR PLAN APPROVAL,
 INCLUDE MANUFACTURER'S SPECIFICATION SHEET ON THIS
 PRODUCT, SHOWING COMPATIBILITY WITH SELECTED LOAD
 CENTER.
 2] AFFIX LABEL INSIDE COMBINER PANEL (IMMEDIATELY
 ADJACENT TO BACKFED BREAKER) INDICATING PURPOSE AS PV
 DISCONNECT/RAPID SHUTDOWN SWITCH. FOR PLAN APPROVAL,
 SHOW SAMPLE OF THIS LABEL ON SHEET E-602.
 3] AFFIX LABEL ON EXTERIOR COVER OF COMBINER PANEL
 INDICATING THE PRESENCE OF A PV DISCONNECT/RAPID
 SHUTDOWN SWITCH WITHIN THE ENCLOSURE. FOR PLAN
 APPROVAL, SHOW SAMPLE OF THIS LABEL ON SHEET E-602.
  
2024-04-05 14:58:11.00000REVISED PLANS KELCIE@CASTAWAYSENERGY.COM

Review Stop BUILDING BUILDING DEPARTMENT
Rev No 1 Status D Date 03-21-2024 Cont ID  
Sent By cdorman Date 03-21-2024 Time 12:51 Rev Time 0.00
Received By cdorman Date 03-20-2024 Time 09:04 Sent To  
Notes
2024-03-21 12:51:26.00000SHEET E-601: SHOW A SEPARATE DISCONNECTING MEANS FOR
 THE PV SYSTEM COMPLYING WITH 690.13 (A), (B), (D), &
 (E). THE DISCONNECTING MEANS MUST BE READILY ACCESSIBLE
 AND LOCKABLE, AND IF INTENDED TO FUNCTION AS THE RAPID
 SHUTDOWN SWITCH, MUST BE LOCATED ON THE EXTERIOR OF THE
 HOUSE, 690.12 (C).
 IF POSSIBLE, SUBMIT ONLY THE AFFECTED SHEET E-601.
  
 NOTE ADDED 4/4/24: TO CLARIFY INTENT OF ABOVE
 REQUIREMENT, SEE TEXT OF 690.12 (C), SECOND PARAGRAPH:
 "FOR A SINGLE PV SYSTEM, THE RAPID SHUTDOWN INITIATION
 DEVICE SHALL OCCUR BY THE OPERATION OF ANY SINGLE
 INITIATION DEVICE". NOTE REQUIREMENT IN PREVIOUS
 PARAGRAPH THAT THIS DEVICE MUST BE AT A READILY
 ACCESSIBLE LOCATION ON THE EXTERIOR OF ONE-FAMILY
 DWELLINGS. THIS INFORMATION HAS BEEN COMMUNICATED TO
 THE CONTRACTOR OF RECORD BY EMAIL. ALL ASSOCIATED
 EMAILS WILL BE RETAINED IN THE PERMIT FOLDER IN PDF
 FORMAT.
2024-03-20 09:18:19.00000EMAILED IN FROM KELCIE@CASTAWAYSENERGY.COM