Plan Review Details - Permit 20120145
Plan Review Stops For Permit 20120145
Review Stop BUILDING BUILDING DEPARTMENT
Rev No 3 Status A Date 05-11-2021 Cont ID  
Sent By cdorman Date 05-11-2021 Time 08:14 Rev Time 0.00
Received By cdorman Date 05-03-2021 Time 15:55 Sent To  
Notes
2021-05-10 12:33:04.00000FLPERMITS@EMPIRESOLARGROUP.COM
2021-05-03 15:55:45.00000RECEIVED REVISED PLANS FOR THIS JOB, MAILED IN, BROUGHT
 TO BLDG FROM ZONING 05/03/2021, 3:55 PM,

Review Stop BUILDING BUILDING DEPARTMENT
Rev No 2 Status D Date 04-05-2021 Cont ID  
Sent By cdorman Date 04-05-2021 Time 15:20 Rev Time 0.00
Received By cdorman Date 04-05-2021 Time 12:54 Sent To  
Notes
2021-04-05 15:20:25.00000REPLACE SHEET 07:
 1] CHANGE CONDUCTOR BETWEEN 7600W INVERTER AND COMBINER
 PANEL TO #8 CU. AMPACITY IS DETERMINED BASED ON 75
 DEGREES C TERMINAL TEMPERATURE, ASSUMED ON INVERTER AND
 CIRCUIT BREAKER. #10 IS RATED FOR 40A ONLY AT 90
 DEGREES C.
 2] 3/0 CONDUCTORS BETWEEN SERVICE PANEL AND GATEWAY,
 AND BETWEEN GATEWAY AND 200A SUBPANEL, ARE IDENTIFIED
 AS "PV WIRE" ON SCHEDULE. SHOW AS THWN-2.
 3] SHOW CONDUIT/CONDUCTORS FROM TESLA GENERATION PANEL
 TO POWERWALLS.
 4] ADD NOTE INDICATING THAT GUTTER SPACE IN SERVICE
 PANEL WILL NOT BE FILLED MORE THAN 75% DUE TO TAPS TO
 EXISTING FEEDERS
  
 PROVIDE SPECIFICATION SHEETS FOR TESLA GATEWAY &
 POWERWALLS
  
  
2021-04-05 12:54:35.00000REVISIONS DROPPED OFF

Review Stop BUILDING BUILDING DEPARTMENT
Rev No 1 Status A Date 12-10-2020 Cont ID  
Sent By cdorman Date 12-10-2020 Time 14:40 Rev Time 0.00
Received By cdorman Date 12-07-2020 Time 11:38 Sent To  
Notes
***NONE***