Case Number CE12020102 complainant  
Case Date 02-10-2012 address  
Origination PHONE - TELEPHONE CALL RECEIVED Status O - OPEN (UNVERIFIED)
Operator cshackel Officer OFFICE
Fines Balance $0.00
Lien Balance $0.00
Total Balance $0.00
Property On Case
STRAP NBR C-14-37-29-150-1000-0310 Owner BABSON PROPERTIES LLC
Unit   Owner Address 1277 N KILLIAN DR
Property Address 1526 WASHINGTON BLVD City/State/Zip LAKE PARK FL 33403
City/State/Zip LAKE PLACID FL 33852 Phone  
Case Description
APPEARS TO BE BUILDING A DOCK IN THE WATER, NO
PERMIT.
Inspections/Events Detail
DATETIMEINSPECTION / EVENT TYPEINSTRUCTIONS / COMMENTS
05-04-201204:12 PMREINSPECTIONI WENT TO THE SITE TO ATTEMPT TO
DETERMINE IF ANY ADDITIONAL WORK HAS
BEEN DONE, OR IF THE JOB HAS INCREASED
IN SIZE FROM THE ORIGINAL WORK. THE
PICTURES I SAW SHOWED FOUR POST IN THE
WATER W/2 BOARDS ATTACHED HORIZONTALLY
TO THE POSTS. THERE WAS NO DOCK AND THE
BOAT SIMPLY PULLED IN BETWEEN THE
BOARDS. WHEN I WENT TO THE SITE TODAY I
FOUND A 15X25 DOCK W/DECKING. THERE IS
A 40" ADDITION TO THE NORTH SIDE OF THE
DOCK WITH AN ADDITIONAL ROW OF POSTS
ADDED TO SUPPORT THE NEW OUTSIDE EDGE.
THERE HAS BEEN SIGNIFICANT WORK DONE ON
THE OLD 2-BOARD BOAT SLIP. CONVERTING IT
TO A COMPLETE DOCK W/DECKING.
05-01-201204:09 PMREINSPECTIONRECEIVED A CALL FROM MR CULLEN AT 4:30
PM ASKING ABOUT THE PROCESS TO OBTAIN A
PERMIT FOR HIS DOCK. HE ASKED THAT I
MAIL HIM AN APPLICATION WHICH I DID. I
TOLD HIM PART OF THE PROCESS WAS TO
OBTAIN A SIGN OFF FROM THE ZONING DEPT &
HE SAID HE WOULD DRAW UP A PLAN FOR THE
DOCK AND GET THE PERMIT.
02-14-201208:31 AMGENERAL BLDG COMPLAINTRFS WENT BACK TO SITE. GAVE OWNER A
STOP WORK ORDER ON DOCK. NEW COMPLAINT
FROM NEIGHBOR THAT THE DOCK IS ON HIS
PROPERTY, AND THAT ITS A NEW DOCK, NOT
RE-DECKING. TOLD OWNER TO COME IN
W/PLAN TO OBTAIN PERMIT.
02-13-201204:23 PMCLOSE COMPLAINTCASE CLOSED BY BSZOKA
02-13-201204:23 PMINITIAL INSPECTIONOWNER IS BUILDING A PERGOLA ON AN
EXISTING SLAB FOR WHICH NO PERMIT IS
REQUIRED, AND HE IS ALSO REDECKING HIS
DOCK FOR WHICH NO PERMIT IS NEEDED. HE
IS PLANNING TO PUT A ROOF ON THE DOCK AT
A LATER DATE. I TOLD HIM WHEN HE DOES
THE ROOF HE WOULD NEED AN ENGINEERED
BUILDING PLAN AND A PERMIT FOR THE NEWLY
CONSTRUCTED ROOF.
02-10-201201:53 PMCREATE COMPLAINTCOMPLAINT RECORDED BY CSHACKEL
Copyright © 2008 – THE PLUS SERIES ® – All Rights Reserved